1212 Maryland St
San Francisco permit 202212229038 · Potrero Hill
Mayor dir 13-01 & 17-02 priority project: erect a 8-story, type 1b, residential/mixed use building, with 105 residential units, retail, assembly, office. (block 7b)
- Filed
- Dec 22, 2022
- Issued
- Oct 25, 2023 (10 months after filing)
- Completed
- Aug 28, 2026 (34 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 154 stops across 8 departments
- Comments issued
- 33 times, by Public Utilities, Building Inspection, Public Health, Public Works, Fire Department, Permit Center
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2022 | Dec 23, 2022 | — |
CON CON-BOND | Dec 27, 2022 | Sep 20, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 27, 2022 | Apr 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 27, 2022 | Sep 22, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Apr 13, 2023 | Jul 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 13, 2023 | Aug 11, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 13, 2023 | Aug 16, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2023 | Apr 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 13, 2023 | Jul 28, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 6, 2023 | Jul 20, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 4, 2023 | Aug 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 15, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 18, 2023 | Sep 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2023 | Sep 21, 2023 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Sep 18, 2023 | Sep 18, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2023 | Oct 25, 2023 | Administrative |
Addendum 1: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 27, 2023 | Oct 27, 2023 | Administrative |
Public health review Public Health · HEALTH | Oct 27, 2023 | Nov 7, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 27, 2023 | Apr 11, 2024 | Administrative |
Public health review Public Health · HEALTH | Apr 10, 2024 | Apr 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 11, 2024 | Apr 12, 2024 | Administrative |
Addendum 2: Excavation,rough grading,soil improvement ddc
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 8, 2023 | Nov 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Dec 1, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 8, 2023 | Jan 16, 2024 | — |
Building plan review Building Inspection · BLDG | Jan 16, 2024 | Jan 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 16, 2024 | Jan 25, 2024 | Administrative |
Addendum 3: Foundation,underground utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 8, 2023 | Nov 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Nov 30, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2023 | Nov 13, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 8, 2023 | Apr 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 27, 2023 | Jan 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 27, 2023 | Mar 20, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2023 | Dec 27, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | Mar 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Mar 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 28, 2024 | Mar 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2024 | Apr 1, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2024 | Apr 3, 2024 | Administrative |
Addendum 4: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 8, 2023 | Nov 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Dec 1, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2023 | Nov 13, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 8, 2023 | Apr 15, 2024 | — |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2023 | Dec 27, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Mar 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 27, 2024 | Mar 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 5, 2024 | Apr 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2024 | Apr 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2024 | Apr 15, 2024 | Administrative |
Addendum 5: Arch,civil,landscape,mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2024 | Mar 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2024 | Mar 4, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 26, 2024 | Feb 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 29, 2024 | Feb 29, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 1, 2024 | Mar 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 4, 2024 | Apr 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 4, 2024 | Mar 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 4, 2024 | Apr 22, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 4, 2024 | Mar 6, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 4, 2024 | Mar 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 4, 2024 | May 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 4, 2024 | Oct 30, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 7, 2024 | Apr 17, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 14, 2024 | May 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Aug 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2024 | Jul 30, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 25, 2024 | Aug 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2024 | Aug 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2024 | Sep 11, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2024 | Sep 16, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 20, 2024 | Sep 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 9, 2024 | Oct 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2024 | Oct 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 23, 2024 | Oct 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2024 | Oct 24, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 23, 2024 | Oct 30, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 23, 2024 | Oct 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2024 | Oct 28, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2024 | Oct 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 23, 2024 | Oct 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2024 | Nov 4, 2024 | Administrative |
Addendum 6: Ext metal stud framing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2024 | Sep 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 9, 2024 | Sep 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 9, 2024 | Sep 9, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 9, 2024 | Sep 9, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2024 | Sep 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 12, 2024 | Oct 3, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 12, 2024 | Sep 24, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 12, 2024 | Oct 18, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 24, 2024 | Sep 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Oct 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 16, 2024 | Oct 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 18, 2024 | Oct 21, 2024 | Administrative |
Addendum 7: Stormwater
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 15, 2024 | Mar 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 20, 2024 | Mar 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2024 | Mar 22, 2024 | Administrative |
Plumbing plan check Building Inspection · PID-PC | Mar 22, 2024 | Mar 25, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 22, 2024 | Mar 26, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2024 | Mar 26, 2024 | Administrative |
Addendum 8: Fire sprinkler protection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 6, 2024 | Mar 15, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 14, 2024 | Mar 14, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Apr 26, 2024 | May 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 3, 2024 | May 3, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 3, 2024 | May 7, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 3, 2024 | Jun 12, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 17, 2024 | Jun 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2024 | Jun 13, 2024 | Administrative |
Addendum 9: Fire alarm,2-way ecs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2024 | Sep 23, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 20, 2024 | Sep 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2024 | Sep 23, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 23, 2024 | Oct 23, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 23, 2024 | Mar 19, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 19, 2024 | Dec 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 21, 2025 | Mar 18, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 19, 2025 | Mar 25, 2025 | Administrative |
Addendum 10: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 15, 2024 | Oct 24, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 21, 2024 | Oct 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 25, 2024 | Oct 25, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 25, 2024 | Nov 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 25, 2024 | Jan 27, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Nov 27, 2024 | Nov 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2025 | Jan 27, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jan 27, 2025 | Jan 28, 2025 | Administrative |
Addendum 11: Steel stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 30, 2024 | Jun 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 5, 2024 | Jun 5, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 10, 2024 | Jun 10, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2024 | Jun 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 10, 2024 | Jun 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 10, 2024 | Jun 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 10, 2024 | Jul 1, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2024 | Jul 3, 2024 | Administrative |
Addendum 12: Photovoltaic system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 5, 2024 | Nov 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2024 | Nov 20, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2024 | Nov 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 15, 2024 | Nov 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 20, 2024 | Dec 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2024 | Dec 3, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Nov 20, 2024 | Dec 16, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 20, 2024 | Dec 18, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Nov 27, 2024 | Dec 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Dec 19, 2024 | Administrative |
Addendum 13: Ebm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 12, 2024 | Nov 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 21, 2024 | Nov 21, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Dec 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 21, 2024 | Dec 4, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Dec 10, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 10, 2024 | Dec 12, 2024 | Administrative |
Addendum 14: Code signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 23, 2024 | Jan 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2025 | Jan 7, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 7, 2025 | Jan 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 7, 2025 | Jan 27, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 7, 2025 | Jan 28, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Jan 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $35,000,000
| Name | Role | License on permit |
|---|---|---|
| Ryan Joshua Jang Leddy Maytum Architects | Architect | C33368 |
| Randall James Girouard | Engineer | S5357 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026