1490 Mason St
San Francisco permit 202212239075 · Chinatown
Priority process per ab004: chinatown public health ctr, renovation of exterior/interior/broadway tunnel below clinic improvement. some site reno proposed to improve accessibility along mason st entry & pedestrian access for broadway tunnel. incl storage ocupancy (s-2)
- Filed
- Dec 23, 2022
- Issued
- Mar 28, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 81 stops across 6 departments
- Comments issued
- 18 times, by Building Inspection, Public Works, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 23, 2022 | Dec 23, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 23, 2022 | Oct 24, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Sep 6, 2023 | Sep 11, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 25, 2023 | Dec 13, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Dec 11, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 11, 2023 | Mar 21, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2023 | Dec 18, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 12, 2023 | Feb 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2023 | Dec 18, 2023 | Approved |
Public Works disability access review Public Works · PW-DAC | Dec 12, 2023 | Dec 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2023 | Jan 22, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 12, 2023 | Dec 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 24, 2024 | Feb 6, 2024 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Jan 24, 2024 | Feb 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 24, 2024 | Jan 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 24, 2024 | Jan 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2024 | Jan 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 28, 2024 | Mar 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 29, 2024 | Mar 6, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Feb 29, 2024 | Mar 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 29, 2024 | Mar 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 29, 2024 | Mar 12, 2024 | Approved |
Public Works disability access review Public Works · PW-DAC | Feb 29, 2024 | Mar 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2024 | Mar 28, 2024 | Administrative |
Addendum 1: Demolition, foundations & structural, arch, mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 15, 2024 | Apr 25, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 17, 2024 | Apr 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 19, 2024 | Apr 19, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 19, 2024 | Apr 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 26, 2024 | May 29, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | May 29, 2024 | May 1, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 30, 2024 | Jul 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 30, 2024 | Aug 7, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2024 | Jun 28, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 30, 2024 | Jul 2, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 30, 2024 | Jun 26, 2024 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | May 30, 2024 | Jun 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | Jun 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2024 | Jun 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 22, 2024 | Jul 23, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 9, 2024 | Dec 24, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 10, 2025 | Jun 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 2, 2025 | Jul 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 2, 2025 | Jul 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 8, 2025 | Jul 8, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 10, 2025 | Oct 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Jan 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Jan 26, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 21, 2026 | Jan 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Jan 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 22, 2026 | Jan 23, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 23, 2026 | Feb 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 24, 2026 | Apr 2, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 31, 2026 | Mar 31, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 2, 2026 | Apr 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2026 | Apr 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 2, 2026 | Apr 14, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Apr 2, 2026 | Apr 8, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2026 | Apr 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2026 | Apr 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2026 | May 12, 2026 | Administrative |
Addendum 7: Structural revisions to s-1
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 5, 2026 | Aug 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2026 | Aug 21, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 21, 2026 | Aug 31, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 21, 2026 | Aug 31, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 21, 2026 | Sep 21, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 21, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Oct 21, 2026 | Oct 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 21, 2026 | Oct 21, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 8: Buckling restrained brace & frames
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2026 | Sep 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2026 | Sep 11, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 11, 2026 | Oct 1, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Sep 11, 2026 | Oct 1, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 11, 2026 | Sep 23, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Sep 11, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $42,487,700
| Name | Role | License on permit |
|---|---|---|
| Raymond Lui Dpw.Infrastrucure Design | Engineer | S-4094 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026