725 Davis St
San Francisco permit 202212239076 · Financial District/South Beach
Warm shell t.i. for a future cafe tenant. mep work to be design-build
- Filed
- Dec 23, 2022
- Issued
- Mar 13, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Disability access review Mayor's Office on Disability · MOD | Nov 28, 2022 | Nov 28, 2022 | — |
Intake Building Inspection · INTAKE | Dec 23, 2022 | Dec 23, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 23, 2022 | Dec 23, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 23, 2022 | Dec 23, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2022 | Dec 23, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Dec 23, 2022 | Dec 23, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Dec 23, 2022 | Dec 23, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 23, 2022 | Dec 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2022 | Dec 23, 2022 | — |
Intake Building Inspection · INTAKE | Jan 6, 2023 | Jan 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 6, 2023 | Jan 6, 2023 | — |
Public health review Public Health · HEALTH | Jan 6, 2023 | Jun 6, 2023 | — |
Intake Building Inspection · INTAKE | Jun 6, 2023 | Jun 6, 2023 | — |
Public health food review Public Health · HEALTH-FD | Jun 6, 2023 | Jun 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 16, 2023 | Jun 16, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 23, 2023 | Jun 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 23, 2023 | Jul 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2023 | Jun 26, 2023 | — |
Disability access review Mayor's Office on Disability · MOD | Jun 27, 2023 | Jul 12, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 13, 2023 | Mar 13, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $927,000
| Name | Role | License on permit |
|---|---|---|
| J Aaron Thornton Leddy Maytum Stacy Architects | Architect | C35066 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022