210 Spruce St
San Francisco permit 202212239113 · Presidio Heights
Add 303 sf of (n) unconditioned storage space at (e) garage, replace stair from garage to basement, interior partition changes, plumbing/electrical @ garage/basement. no change to bldg envelope
- Filed
- Dec 23, 2022
- Issued
- Apr 10, 2024 (16 months after filing)
- Completed
- Dec 17, 2025 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Public Works, Public Utilities
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 23, 2022 | Dec 23, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2022 | Dec 23, 2022 | — |
Intake Building Inspection · INTAKE | Aug 15, 2023 | Aug 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2023 | Aug 22, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 22, 2023 | Aug 22, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Aug 22, 2023 | Aug 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2023 | Aug 28, 2023 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Aug 25, 2023 | Aug 25, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 28, 2023 | Oct 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 5, 2023 | Oct 11, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 12, 2023 | Oct 20, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2023 | Oct 25, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2023 | Dec 8, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2024 | Feb 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Mar 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2024 | Mar 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2024 | Mar 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2024 | Mar 15, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 19, 2024 | Mar 19, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 19, 2024 | Apr 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $225,000
| Name | Role | License on permit |
|---|---|---|
| Eric Harry Hartz Gast Architects | Architect | C33994 |
| Lawrence Tik Man Wong L Wong Engineering | Engineer | 5135 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2017