1639 Oak St
San Francisco permit 202212239139 · Haight Ashbury
Scope of work includes alterations to the ext plaza occupying the southeast corner of the property at 1639 oak st., including alterations to an ext stair leading to the parking garage, a new ramped approach to the ext plaza and a reshaped flow-thru planter
- Filed
- Dec 23, 2022
- Issued
- Sep 28, 2023 (9 months after filing)
- Completed
- May 16, 2025 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 14 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 6, 2023 | Jan 9, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 10, 2023 | Mar 28, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 10, 2023 | Sep 22, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2023 | Jul 21, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 29, 2023 | Jul 24, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 29, 2023 | Sep 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 29, 2023 | Apr 5, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 21, 2023 | Jul 26, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 21, 2023 | Sep 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2023 | Aug 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 5, 2023 | Sep 12, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 6, 2023 | Sep 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2023 | Sep 22, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2023 | Sep 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| William Douaire Bondy Starkweather/Bondy | Architect | C19253 |
| Alex Filatov Murphy Burr Curry Inc. | Engineer | C65023 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026