900 North Point St #534
San Francisco permit 202212239140 · Russian Hill
T.i ghirardell tenant space with in clock tower bldg 3/f and 4/f. interior only. no exterior work. work includes new partitions, lighting, millwork.
- Filed
- Dec 23, 2022
- Issued
- Feb 24, 2023 (2 months after filing)
- Completed
- Sep 14, 2023 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 10 stops across 5 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 23, 2022 | Dec 23, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 18, 2023 | Jan 18, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 19, 2023 | Jan 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2023 | Jan 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 23, 2023 | Jan 23, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 9, 2023 | Feb 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2023 | Feb 10, 2023 | — |
Public health review Public Health · HEALTH | Feb 14, 2023 | Feb 14, 2023 | — |
Apartment and hotel inspection Building Inspection · HIS | Feb 24, 2023 | Feb 24, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2023 | Feb 24, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $666,750
| Name | Role | License on permit |
|---|---|---|
| William J Commer | Architect | C-28438 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2011