1 Zoo Rd
San Francisco permit 202212239143 · Lakeshore
Two - one story addition of an animal holding spaces and two outdoor animal exhibit spaces adjacent to exisitng animal holding facility.
- Filed
- Dec 23, 2022
- Issued
- Jan 24, 2025 (25 months after filing)
- Completed
- Aug 20, 2025 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 4 departments
- Comments issued
- 9 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2022 | Jan 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 6, 2023 | Sep 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 6, 2023 | Jan 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Oct 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 3, 2024 | Oct 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2024 | Sep 19, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 3, 2024 | Sep 9, 2024 | Approved |
Disability access review Mayor's Office on Disability · MOD | Sep 16, 2024 | Sep 16, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 2, 2024 | Oct 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2024 | Oct 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 17, 2024 | Oct 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 1, 2024 | Nov 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 1, 2024 | Nov 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2024 | Nov 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 1, 2024 | Nov 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 1, 2024 | Nov 6, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 25, 2024 | Nov 25, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 26, 2024 | Dec 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 26, 2024 | Nov 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 26, 2024 | Dec 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 26, 2024 | Dec 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 26, 2024 | Dec 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2024 | Jan 13, 2025 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jan 13, 2025 | Jan 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $119,978
| Name | Role | License on permit |
|---|---|---|
| Frank Sung Fung Ed2 International | Architect | C8858 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2018