580 Banks St
San Francisco permit 202212279156 · Bernal Heights
Demo & relocate interior partitions.replace all siding & wdws.raised partial area of roof to add clerestory.add powder rm, relocate (e) bathrms & replace all fixtures.replace kitchen fixtures,int stair & floor finish,ext backyard stair & fence, add on grade wood deck.replace a portion of retaining
- Filed
- Dec 27, 2022
- Issued
- Jan 30, 2024 (13 months after filing)
- Completed
- Sep 11, 2026 (31 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- Twice, by Building Inspection, Public Works
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 27, 2022 | Jan 3, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 3, 2023 | May 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 3, 2023 | Jan 24, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Mar 28, 2023 | May 17, 2023 | — |
Building plan review Building Inspection · BLDG | May 23, 2023 | Jul 31, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2023 | Dec 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 23, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 23, 2023 | Jan 24, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 1, 2023 | Jan 3, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Dec 18, 2023 | Dec 18, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2023 | Dec 20, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jan 8, 2024 | Jan 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2024 | Jan 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 24, 2024 | Jan 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 24, 2024 | Jan 30, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $471,270
| Name | Role | License on permit |
|---|---|---|
| Bruce Christian Prescott Santos Prescott & Assoc. | Architect | C23687 |
| Stan Michael Wu Smw & Associates, Inc. | Engineer | 4665 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025