Scope of work
As written on the permit application.

Horizontal rear addition on 2/f & 3/f. new windows and doors at addition. new half-bath/laundy and kitchen expansion on 2/f. new primarty suite at 3/f with new skylight at (e) roof. add new adu on 1st floor.

Timeline
Key dates from the city record.
Filed
Dec 27, 2022
Issued
Jul 9, 2025 (30 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 5 departments
Comments issued
9 times, by Building Inspection, Public Works
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 4, 2023—

Zoning review

Planning · CP-ZOC

Jul 12, 2023—

Planning neighborhood notice

Planning · CP-NP

Jun 9, 2023—

Zoning review

Planning · CP-ZOC

Dec 10, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 9, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 17, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 11, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 11, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 6, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 12, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 21, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 20, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 29, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 3, 2023Issued Comments

Urban forestry

Public Works · DPW-BUF

Nov 21, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 24, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 8, 2023Approved

Fire prevention review

Fire Department · SFFD

Dec 20, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Jul 31, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Aug 26, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 16, 2024Approved

Permit Processing Center

Building Inspection · PPC

Dec 19, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 17, 2024Approved

Development fee collection

Building Inspection · DFCU

Dec 19, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jul 9, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$325,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Christian J Dauer

Chr Dauer Architect

ArchitectC28302
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202212279169 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record