1135 Powell St
San Francisco permit 202212279199 · Chinatown
Priority process: renovation to listed historic library(1921). partial demo of int spaces of historic bldg & 1996 renovation work. new mech, elec, and fire protection sys will be provided throughout (e) bldg. project is designed to leadership in energy efficient design (leed) rating of gold
- Filed
- Dec 27, 2022
- Issued
- May 28, 2024 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 55 stops across 6 departments
- Comments issued
- 18 times, by Fire Department, Building Inspection, Permit Center, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 27, 2022 | Dec 28, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 28, 2022 | Apr 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 28, 2022 | May 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 16, 2023 | Feb 17, 2023 | Denied |
Fire prevention review Fire Department · SFFD | Aug 3, 2023 | Aug 16, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 3, 2023 | Aug 22, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2023 | Aug 22, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2023 | Dec 8, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 13, 2023 | Nov 13, 2023 | Approved |
Public Works disability access review Public Works · PW-DAC | Dec 27, 2023 | Jan 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Apr 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 26, 2024 | May 2, 2024 | Approved |
Public Works disability access review Public Works · PW-DAC | Apr 26, 2024 | Apr 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 26, 2024 | Apr 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2024 | May 1, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2024 | Apr 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 2, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 2, 2024 | May 2, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | May 3, 2024 | May 28, 2024 | Administrative |
Addendum 1: Arch,structural,civil, mep/ele
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 10, 2024 | Jun 17, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 11, 2024 | Jun 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 13, 2024 | Jun 13, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 14, 2024 | Jun 14, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 23, 2024 | Sep 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 3, 2024 | Sep 3, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 6, 2024 | Sep 6, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 10, 2024 | Sep 10, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2024 | Sep 13, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 13, 2024 | Nov 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 13, 2024 | Nov 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2024 | Oct 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 13, 2024 | Oct 16, 2024 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 13, 2024 | Oct 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2024 | Sep 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2024 | Sep 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 13, 2024 | Sep 9, 2026 | Administrative |
Electrical plan review Building Inspection · MECH-E | Oct 3, 2024 | Oct 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 17, 2025 | Oct 14, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 17, 2025 | Oct 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 17, 2025 | Sep 25, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 17, 2025 | Sep 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 17, 2025 | Sep 19, 2025 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 17, 2025 | Oct 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2025 | Sep 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2025 | Sep 19, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 17, 2025 | Oct 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 7, 2026 | Aug 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 7, 2026 | Aug 12, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 7, 2026 | Aug 10, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 7, 2026 | Sep 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2026 | Sep 1, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Aug 7, 2026 | Aug 31, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2026 | Aug 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 7, 2026 | Aug 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2026 | Oct 29, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $19,000,000
| Name | Role | License on permit |
|---|---|---|
| Nancy Gail Goldenberg Treanorhl | Architect | C-25019 |
| Eugene Yu-Ming Tuan Tuan & Robinson Str. Engineer | Engineer | S3982 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025