1100 Revere Av
San Francisco permit 202212279212 · Bayview Hunters Point
To erect a one-story, type 3-b, warehouse.
- Filed
- Dec 27, 2022
- Issued
- Oct 25, 2023 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 68 stops across 6 departments
- Comments issued
- 22 times, by Building Inspection, Fire Department, Public Works, Public Health
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2022 | Feb 16, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 16, 2023 | May 4, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 16, 2023 | Oct 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | May 4, 2023 | Sep 27, 2023 | — |
Fire prevention review Fire Department · SFFD | May 4, 2023 | Sep 13, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | May 4, 2023 | May 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2023 | Sep 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2023 | Oct 5, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 28, 2023 | Sep 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2023 | Oct 4, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2023 | Oct 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 28, 2023 | Oct 6, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Oct 6, 2023 | Oct 10, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2023 | Oct 25, 2023 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 15, 2023 | Nov 15, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 15, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Jan 25, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 20, 2023 | Jan 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2023 | Dec 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 20, 2023 | Jun 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2023 | Nov 20, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 20, 2023 | Nov 30, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2023 | Nov 21, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 27, 2023 | Nov 27, 2023 | Issued Comments |
Public Health HEALTH-MH | Mar 15, 2024 | Mar 15, 2024 | Issued Comments |
Public Health HEALTH-MH | Apr 17, 2024 | May 17, 2024 | Issued Comments |
Public Health HEALTH-MH | May 24, 2024 | May 24, 2024 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jun 3, 2024 | Jun 12, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 3, 2024 | Jun 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jun 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2024 | Jun 10, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 4, 2024 | Jun 11, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2024 | Jun 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2024 | Jun 13, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 24, 2024 | Aug 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Aug 7, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 25, 2024 | Jul 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 25, 2024 | Jul 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2024 | Jul 29, 2024 | Approved |
Public Health HEALTH-MH | Jul 25, 2024 | Jul 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 25, 2024 | Jul 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2024 | Jul 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2024 | Jul 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 30, 2024 | Aug 30, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2024 | Oct 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 14, 2024 | Oct 24, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 15, 2024 | Oct 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2024 | Nov 5, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 31, 2024 | Oct 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 5, 2024 | Nov 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 5, 2024 | Nov 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2024 | Nov 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 5, 2024 | Nov 6, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 5, 2024 | Nov 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2024 | Nov 6, 2024 | Approved |
Public Health HEALTH-MH | Nov 5, 2024 | Nov 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 14, 2024 | Nov 14, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2024 | Nov 14, 2024 | Approved-Stipulated |
Public Health HEALTH-MH | Nov 14, 2024 | Nov 21, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 14, 2024 | Dec 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2024 | Nov 18, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 14, 2024 | Nov 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2024 | Nov 25, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 14, 2024 | Nov 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $1,250,000
| Name | Role | License on permit |
|---|---|---|
| Kevin Michael Skiles Zack/Devito Architecture | Architect | C-28857 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026