Deck, stairs or patio coverFull plan reviewWithdrawn
Street view · Sep 2026
Google Street View of 717 Battery St, Sep 2026
Scope of work
As written on the permit application.

Int courtyard alterations. project proposes to construct a retractable canopy that will partially cover the (e) ground floor courtyard. no change to any of the (e) uses. mep deferred

Timeline
Key dates from the city record.
Filed
Dec 27, 2022
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
9 times, by Building Inspection
Put on hold
Once
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 6, 2023—

Zoning review

Planning · CP-ZOC

Jul 7, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 3, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Aug 11, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Aug 14, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 31, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 19, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jul 19, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 4, 2023Administrative

Structural plan approval

Building Inspection · PAD-STR

Nov 9, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 18, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 19, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 9, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 11, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 24, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 31, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 14, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 16, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 4, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 13, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 11, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 8, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 7, 2024Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Withdrawn
Estimated cost
$1,252,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John Ike

Ike Kligerman Barkley Aia

ArchitectC21590
Ben Au

Holmes Culley

EngineerS4938
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202212279215 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record