717 Battery St
San Francisco permit 202212279215 · Financial District/South Beach
Int courtyard alterations. project proposes to construct a retractable canopy that will partially cover the (e) ground floor courtyard. no change to any of the (e) uses. mep deferred
- Filed
- Dec 27, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 26 stops across 5 departments
- Comments issued
- 9 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 28, 2022 | Jan 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 9, 2023 | Jul 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 9, 2023 | Apr 3, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jul 7, 2023 | Aug 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 7, 2023 | Aug 14, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2023 | Jul 31, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 7, 2023 | Dec 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2023 | Jul 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2023 | Aug 4, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 2, 2023 | Nov 9, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 14, 2023 | Dec 18, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 19, 2023 | Dec 19, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 9, 2024 | Jan 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 11, 2024 | Jan 11, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2024 | Jan 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 31, 2024 | Jan 31, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 14, 2024 | Feb 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2024 | Feb 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 4, 2024 | Mar 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 7, 2024 | Mar 13, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 7, 2024 | Mar 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2024 | Mar 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 7, 2024 | Mar 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2024 | Mar 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2024 | Mar 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2024 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Withdrawn
- Estimated cost
- $1,252,500
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026