121 States St
San Francisco permit 202212289230 · Castro/Upper Market
Construction of a deck at rear of property. reconfiguration of interior nonstructural walls. relocation of hvac and hw heaters. legalization of non-permitted bathroom. no work in public right of way. no work to front of building.
- Filed
- Dec 28, 2022
- Issued
- Jan 12, 2024 (12 months after filing)
- Completed
- Oct 15, 2024 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 50 stops across 5 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Fire Department, Permit Center
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 28, 2022 | Dec 28, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 28, 2022 | Dec 28, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 28, 2022 | Dec 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 28, 2022 | Dec 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Dec 28, 2022 | Dec 28, 2022 | — |
Intake Building Inspection · INTAKE | Jan 4, 2023 | Jan 4, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 4, 2023 | Sep 13, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2023 | Apr 18, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 18, 2023 | Jan 3, 2024 | — |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2023 | Apr 24, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jun 2, 2023 | Jun 8, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 27, 2023 | Jul 27, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jul 27, 2023 | Jul 27, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2023 | Sep 28, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 12, 2023 | Oct 4, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Sep 12, 2023 | Oct 11, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 12, 2023 | Oct 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 6, 2023 | Nov 2, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 10, 2023 | Nov 16, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 13, 2023 | Nov 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 1, 2023 | Dec 7, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 4, 2023 | Dec 4, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 5, 2023 | Jan 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2023 | Dec 6, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 5, 2023 | Dec 7, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2023 | Dec 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 7, 2023 | Dec 7, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2024 | Jan 12, 2024 | Administrative |
Addendum 1: Arch structural t24 final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2024 | Feb 16, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 14, 2024 | Feb 14, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 14, 2024 | Feb 14, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 16, 2024 | Feb 16, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2024 | Feb 27, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 22, 2024 | Feb 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 27, 2024 | Feb 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2024 | Feb 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Mar 18, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 27, 2024 | Apr 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2024 | Mar 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 27, 2024 | Feb 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2024 | Feb 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 27, 2024 | May 29, 2024 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | May 7, 2024 | May 7, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 14, 2024 | May 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 15, 2024 | May 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2024 | May 28, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | May 15, 2024 | May 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2024 | May 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2024 | May 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 29, 2024 | May 31, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $87,000
| Name | Role | License on permit |
|---|---|---|
| Nicholas C Thomas Nicolas Thomas | Architect | C38546 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026