340 Fell St
San Francisco permit 202212289303 · Hayes Valley
Renovate two story portion into an electrical automobile service center and one story portion will be an automobile showroom. building does not have an elevator per cbc 11b-206.2.3 exception 1.1 the project includes core and shell modifications the ti willl be submitted under separate permit.
- Filed
- Dec 28, 2022
- Issued
- Jun 26, 2024 (18 months after filing)
- Completed
- Apr 3, 2026 (21 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 37 stops across 7 departments
- Comments issued
- 8 times, by Public Works, Building Inspection, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 28, 2022 | Dec 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2023 | Feb 7, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 17, 2023 | Feb 17, 2023 | — |
Public health review Public Health · HEALTH | Apr 12, 2023 | Apr 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 14, 2023 | Apr 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2023 | May 5, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 19, 2023 | May 19, 2023 | — |
Intake Building Inspection · INTAKE | Aug 30, 2023 | Aug 30, 2023 | Administrative |
Electrical plan review Building Inspection · MECH-E | Aug 30, 2023 | Aug 30, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 30, 2023 | Aug 30, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 31, 2023 | Aug 31, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2023 | Sep 8, 2023 | Approved |
Public health review Public Health · HEALTH | Sep 12, 2023 | Sep 12, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 12, 2023 | Sep 12, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2023 | Oct 4, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 4, 2023 | Jan 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 4, 2023 | Jan 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2024 | Jan 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2024 | Feb 6, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 5, 2024 | Feb 7, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 9, 2024 | Feb 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Mar 15, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 13, 2024 | Mar 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2024 | Apr 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 18, 2024 | Apr 18, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 19, 2024 | Apr 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2024 | Apr 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2024 | Apr 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 29, 2024 | May 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 16, 2024 | May 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2024 | May 24, 2024 | Approved |
Public health review Public Health · HEALTH | May 28, 2024 | May 28, 2024 | Issued Comments |
Public health review Public Health · HEALTH | May 28, 2024 | May 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 29, 2024 | Jun 17, 2024 | Approved |
Public Health HEALTH-MH | Jun 3, 2024 | Jun 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 20, 2024 | Jun 20, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2024 | Jun 26, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $5,000,000
| Name | Role | License on permit |
|---|---|---|
| Kevin Keith Albaugh Mbh | Engineer | C17768 |
| John Theodore Mc Nulty Mbh Architects | Architect | C18129 |
| Matthew Palmer Frantz Zfa Structural Engineers | Engineer | 5919 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026