171 Shakespeare St
San Francisco permit 202212299328 · Outer Mission
To erect 3 stories, 1 basement, type v-b, 2 dwelling units residential (r-3)
- Filed
- Dec 29, 2022
- Issued
- Apr 27, 2026 (40 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 36 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Permit Center
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2022 | Jan 4, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 4, 2023 | Apr 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 4, 2023 | Sep 23, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 24, 2023 | Oct 26, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 24, 2023 | Nov 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 24, 2023 | Aug 4, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2023 | Apr 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2023 | May 16, 2023 | — |
Fire prevention review Fire Department · SFFD | Oct 26, 2023 | Jan 8, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 26, 2023 | Nov 2, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 26, 2023 | Jan 12, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 26, 2023 | Oct 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2023 | Nov 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2023 | Nov 17, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 15, 2023 | Nov 15, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 29, 2024 | Mar 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 1, 2024 | Mar 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 4, 2024 | Mar 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 4, 2024 | Mar 4, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 14, 2024 | Mar 14, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 15, 2024 | Apr 8, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Mar 15, 2024 | Mar 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2024 | Mar 15, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Mar 15, 2024 | Sep 16, 2024 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Apr 11, 2024 | Apr 11, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 11, 2024 | Apr 27, 2026 | Administrative |
Addendum 1: Foundation & superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2026 | Aug 14, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 19, 2026 | Sep 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | In progress | In Progress |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,165,020
| Name | Role | License on permit |
|---|---|---|
| Matthew D Berglund | Architect | c35121 |
| Humza Shahid Chowdhry | Engineer | S6091 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025