4729 18th St
San Francisco permit 202212299333 · Castro/Upper Market
Horizontal addition in rear yard.
- Filed
- Dec 29, 2022
- Issued
- Feb 12, 2025 (25 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2022 | Jan 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 12, 2023 | Nov 16, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 12, 2023 | Jul 17, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Sep 13, 2023 | Sep 25, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 16, 2023 | Jan 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 16, 2023 | Dec 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 16, 2023 | Nov 20, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 16, 2023 | Dec 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 7, 2023 | Dec 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 23, 2024 | Feb 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 5, 2024 | Mar 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 1, 2024 | May 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 17, 2024 | May 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2024 | Jun 24, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 20, 2024 | May 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 24, 2024 | Jul 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 24, 2024 | Jul 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 24, 2024 | Jun 25, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2024 | Jul 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2024 | Feb 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $305,700
| Name | Role | License on permit |
|---|---|---|
| Daniel Bittiker Bittiker Architecture | Architect | C35698 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026