111 Pine St #0
San Francisco permit 202212299343 · Financial District/South Beach
Grd fl: int tenant improvement of (e) lobby. int demo of nonstructural walls, partitions millwork & decorative finishes / elements. new lighting, finishes, and guard desk location. existing storefront to be replaced w/ new. mep:minor lobby hvac repair / upgrades.new lobby lighting and receptacles
- Filed
- Dec 29, 2022
- Issued
- Aug 7, 2024 (19 months after filing)
- Completed
- Sep 10, 2026 (25 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 34 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 8 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 4, 2023 | Jan 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 10, 2023 | Jan 20, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 10, 2023 | Feb 7, 2024 | — |
Building plan review Building Inspection · BLDG | Jan 20, 2023 | Jun 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 20, 2023 | Jul 3, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 20, 2023 | Jul 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 20, 2023 | Jan 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2023 | Feb 14, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 22, 2023 | Aug 30, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 15, 2023 | Jun 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 3, 2023 | Jul 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Aug 2, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 13, 2023 | Aug 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 2, 2023 | Aug 2, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 16, 2023 | Aug 16, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 16, 2023 | Aug 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 16, 2023 | Aug 16, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 16, 2023 | Aug 21, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 16, 2023 | Aug 17, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 8, 2023 | Sep 13, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 8, 2023 | Sep 8, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2023 | Sep 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2023 | Sep 8, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2023 | Oct 18, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2023 | Sep 8, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 18, 2023 | Sep 18, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 18, 2024 | Jan 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 19, 2024 | Jan 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 19, 2024 | Jan 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 19, 2024 | Jan 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 19, 2024 | Jan 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 19, 2024 | Feb 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 19, 2024 | Jan 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2024 | Aug 7, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Anthony Castro Roxas Arxarch | Architect | C-37259 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026