730 Stanyan St
San Francisco permit 202212299363 · Haight Ashbury
Ground flr: ti for use of early childcare & education center. consists of non-structural partitions & finishes, exterior courtyard imrpovements, mep low voltage & fire protection systems will be design build and submitted under separate permits. fixtures & plumbing are shown on plans for ref only.
- Filed
- Dec 29, 2022
- Issued
- Feb 13, 2026 (38 months after filing)
- Completed
- Oct 30, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 29, 2022 | Dec 29, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 29, 2022 | Dec 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 29, 2022 | Apr 26, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 29, 2022 | Dec 29, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2023 | Nov 3, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Mar 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 8, 2024 | Apr 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 22, 2024 | May 30, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2024 | May 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 31, 2024 | Jun 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2025 | Oct 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 16, 2025 | Oct 22, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 16, 2025 | Jan 30, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 31, 2025 | Nov 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2025 | Nov 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 31, 2025 | Nov 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2025 | Nov 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2025 | Nov 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2025 | Jan 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2025 | Dec 31, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2025 | Dec 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2026 | Jan 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2026 | Jan 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 6, 2026 | Jan 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 23, 2026 | Jan 28, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 29, 2026 | Jan 30, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2026 | Feb 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $725,800
| Name | Role | License on permit |
|---|---|---|
| Ryan Joshua Jang Leddy Maytum Stacy Architects | Architect | C33368 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026