6000 Geary Bl
San Francisco permit 202212299421 · Outer Richmond
Extg cheveron gasoline station with the following work: remodel 1989 sq ft convenient store. new building signage. new trash and mechanical enclosure. accessible parking
- Filed
- Dec 29, 2022
- Issued
- Feb 18, 2025 (26 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 40 stops across 7 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 29, 2022 | Dec 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 29, 2022 | Dec 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 4, 2023 | Jan 5, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 4, 2023 | Jan 4, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 6, 2023 | Sep 30, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 25, 2023 | Sep 25, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 2, 2023 | Nov 1, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 2, 2023 | Nov 6, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 6, 2023 | Feb 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 26, 2024 | Jan 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2024 | Feb 7, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 7, 2024 | Feb 21, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 21, 2024 | Mar 15, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 18, 2024 | Mar 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2024 | Mar 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2024 | Mar 26, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 27, 2024 | Apr 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 25, 2024 | Apr 30, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2024 | Apr 29, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2024 | May 3, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 15, 2024 | May 15, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 22, 2024 | May 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2024 | Jun 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 13, 2024 | Jun 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2024 | Jul 8, 2024 | Approved |
Public health review Public Health · HEALTH | Jul 8, 2024 | Jul 8, 2024 | Administrative |
Public Health HEALTH-MH | Jul 8, 2024 | Jul 8, 2024 | Issued Comments |
Public Health HEALTH-HM | Jul 9, 2024 | Jul 9, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Jul 11, 2024 | Jul 11, 2024 | Administrative |
Public health food review Public Health · HEALTH-FD | Jul 11, 2024 | Jul 15, 2024 | Approved |
Public Health HEALTH-MH | Jul 19, 2024 | Jul 19, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Jul 22, 2024 | Aug 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2024 | Aug 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 12, 2024 | Aug 20, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 21, 2024 | Oct 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 11, 2024 | Dec 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Oct 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 17, 2024 | Oct 21, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 21, 2024 | Nov 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Feb 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Gary Michael Semling Stantec Architecture Inc. | Architect | C21541 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026