1 Sgt John V Young St
San Francisco permit 202212299451 · Outer Mission
Existing two story building to be rehabilitated and renovated. work includes upgrades to building structure and replacement of plumbing, electrical and mechanical systems, and interior finishes and fixtures.
- Filed
- Dec 29, 2022
- Issued
- Jun 11, 2026 (41 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 7 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Works, Public Utilities
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2022 | Jan 23, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 24, 2023 | Mar 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Nov 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 10, 2025 | Nov 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 10, 2025 | Jan 12, 2026 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Nov 10, 2025 | Dec 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 10, 2025 | Nov 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 10, 2025 | Nov 20, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 8, 2026 | Jan 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2026 | Jan 22, 2026 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Jan 8, 2026 | Jan 22, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2026 | Jan 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2026 | Jan 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 18, 2026 | Mar 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 18, 2026 | Mar 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 18, 2026 | Mar 24, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Mar 18, 2026 | Mar 25, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2026 | Mar 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2026 | Mar 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2026 | Jun 11, 2026 | Administrative |
Addendum 1: Addendum 1
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 28, 2026 | Oct 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $14,000,000
| Name | Role | License on permit |
|---|---|---|
| Jane Y Chan | Architect | C28245 |
| Thomas Matthew Jasmin San Francisco Public Works | Architect | C32761 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026