1 Sgt John V Young St
San Francisco permit 202212299456 · Outer Mission
To erect a 2-story, type 2a, office building.
- Filed
- Dec 29, 2022
- Issued
- Mar 31, 2026 (39 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 39 stops across 7 departments
- Comments issued
- 8 times, by Building Inspection, Public Works, Public Utilities, Public Health, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2022 | Jan 23, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 24, 2023 | Mar 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Nov 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 10, 2025 | Nov 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 10, 2025 | Jan 12, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Nov 10, 2025 | Dec 12, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 10, 2025 | Nov 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 10, 2025 | Nov 20, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Nov 10, 2025 | Nov 19, 2025 | Administrative |
Public Health HEALTH-MH | Nov 12, 2025 | Nov 12, 2025 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Dec 2, 2025 | Dec 2, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Jan 8, 2026 | Jan 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2026 | Jan 22, 2026 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Jan 8, 2026 | Jan 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2026 | Jan 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2026 | Jan 13, 2026 | Approved |
Public Health HEALTH-MH | Jan 8, 2026 | Jan 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 12, 2026 | Feb 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2026 | Feb 19, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2026 | Feb 17, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Feb 12, 2026 | Feb 17, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2026 | Feb 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2026 | Feb 18, 2026 | Approved |
Public Health HEALTH-MH | Feb 12, 2026 | Feb 19, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 24, 2026 | Feb 24, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 17, 2026 | Mar 31, 2026 | Administrative |
Addendum 1: Site demo, grading and u/g utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 19, 2026 | Sep 4, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 10, 2026 | Sep 21, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 28, 2026 | Oct 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2026 | Oct 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 23, 2026 | Oct 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Oct 23, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Oct 23, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2026 | Oct 27, 2026 | Administrative |
Public Health HEALTH-MH | Oct 23, 2026 | Oct 29, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 23, 2026 | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $15,000,000
| Name | Role | License on permit |
|---|---|---|
| Jane Y Chan | Architect | C28245 |
| Thomas Matthew Jasmin San Francisco Public Works | Architect | C32761 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026