278 Ripley St
San Francisco permit 202212309472 · Bernal Heights
To erect an adu structure. 1-unit, 1 story, type vb.
- Filed
- Dec 30, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 35 stops across 5 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 30, 2022 | Mar 13, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 14, 2023 | Oct 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 14, 2023 | Oct 12, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2023 | Oct 16, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Mar 14, 2023 | May 25, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 14, 2023 | Feb 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2023 | Mar 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2023 | Mar 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 14, 2023 | In progress | — |
Fire prevention review Fire Department · SFFD | Oct 6, 2023 | Oct 30, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2023 | Oct 30, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2023 | Oct 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2023 | Nov 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 31, 2023 | Dec 7, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2023 | Nov 6, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2023 | Nov 6, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2023 | Oct 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Dec 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2023 | Dec 5, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2023 | Dec 13, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 4, 2023 | Dec 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2023 | Dec 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 7, 2023 | Dec 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 16, 2024 | Feb 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Mar 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Feb 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2024 | Feb 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 16, 2024 | Feb 21, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 16, 2024 | Feb 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 4, 2024 | Mar 4, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Mar 11, 2024 | Mar 11, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 18, 2024 | Mar 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2024 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2024 | In progress | In Progress |
Address verification Building Inspection · ADDR | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Approved
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Lisa Wai Sum Tse Integrand Structural Engineer | Engineer | 4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024