62 Dolores Tr
San Francisco permit 202212309533 · Mission
Renovation of (e) single family home. windows. interior renovation of kitchen, living, bedroom and bathrooms.
- Filed
- Dec 30, 2022
- Issued
- Nov 3, 2023 (10 months after filing)
- Completed
- Nov 17, 2025 (24 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 30, 2022 | Jan 27, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2023 | Mar 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 1, 2023 | Mar 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2023 | Mar 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 16, 2023 | Mar 16, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 28, 2023 | Mar 28, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2023 | Mar 28, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 6, 2023 | Apr 6, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 6, 2023 | Apr 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 6, 2023 | Apr 6, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Nov 3, 2023 | Nov 3, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Pho Pho Architects | Architect | C-33844 |
| Humza Shahid Chowdhry Hc Structural Engineering Inc. | Engineer | S-6091 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015