1667 B Fulton St
San Francisco permit 202212309553 · Lone Mountain/USF
Addition of 1 new adu. new foundation & lowered ground floor to provide head clearance for the new units. properties have no street frontage.
- Filed
- Dec 30, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 41 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 13, 2022 | Dec 13, 2022 | — |
Intake Building Inspection · INTAKE | Dec 13, 2022 | Dec 13, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2022 | Feb 8, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 13, 2022 | Jan 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 9, 2023 | Jan 23, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jan 24, 2024 | Feb 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 24, 2024 | Feb 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Apr 4, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2024 | Feb 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 3, 2024 | Apr 3, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 4, 2024 | Apr 10, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 10, 2024 | Apr 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2024 | Apr 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | Apr 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2024 | Apr 30, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2024 | May 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 6, 2024 | May 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2024 | May 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2024 | May 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 15, 2024 | May 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2024 | May 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 17, 2024 | Jul 11, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 11, 2024 | Jul 11, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2025 | Jul 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 1, 2025 | Jul 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2025 | Jul 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 1, 2025 | Jul 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2025 | Jul 16, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 1, 2025 | Jul 7, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2025 | Jul 2, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2025 | Jul 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2025 | Jul 8, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 1, 2025 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $70,000
| Name | Role | License on permit |
|---|---|---|
| Janet Coral Campbell J Campbell Architects Pc | Architect | C-18808 |
| Javier Medina Mark Davis Design | Architect | C34033 |
| Gregory Paul Wallace Gregory Paul Wallace Struct | Engineer | S3308 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026