1140 B Ingerson Av

San Francisco permit 202212309561 · Bayview Hunters Point

ADUFull plan reviewComplete
Scope of work
As written on the permit application.

Convert (e) g/f into one adu (unit b 696sf) per govt code 65852.2(e). other improvements include fire rating existing corridor & stairs on g/f and providing seismic retrofit justifications from structural engineer.new (152sf) elevated deck to provide additional common area for all units.

Timeline
Key dates from the city record.
Filed
Dec 30, 2022
Issued
Dec 30, 2024 (24 months after filing)
Completed
Oct 22, 2026 (22 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
48 stops across 5 departments
Comments issued
15 times, by Building Inspection, Public Works, Fire Department
Put on hold
Once
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2023—

Permit Processing Center

Building Inspection · PPC

Nov 12, 2024Administrative

Zoning review

Planning · CP-ZOC

Jan 30, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 4, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 27, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 5, 2023—

Fire prevention review

Fire Department · SFFD

Sep 20, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jun 26, 2023—

Urban forestry

Public Works · DPW-BUF

Oct 20, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 30, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 29, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 31, 2023Approved

Fire prevention review

Fire Department · SFFD

Mar 7, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 20, 2023Approved

Fire prevention review

Fire Department · SFFD

Oct 20, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 10, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 8, 2024Approved

Zoning review

Planning · CP-ZOC

Feb 27, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Feb 21, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 1, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 5, 2024Approved

Urban forestry

Public Works · DPW-BUF

Mar 15, 2024Approved

Zoning review

Planning · CP-ZOC

May 2, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 22, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 26, 2024Approved

Urban forestry

Public Works · DPW-BUF

May 23, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 25, 2024Approved

Urban forestry

Public Works · DPW-BUF

May 31, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jul 9, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 13, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jul 8, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 10, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 16, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Sep 3, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 6, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 4, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 4, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Sep 11, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 11, 2024Approved

Urban forestry

Public Works · DPW-BUF

Oct 2, 2024Approved

Fire prevention review

Fire Department · SFFD

Oct 17, 2024Approved

Zoning review

Planning · CP-ZOC

Oct 17, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 17, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Oct 11, 2024Approved

Urban forestry

Public Works · DPW-BUF

Oct 18, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 10, 2024Approved

Development fee collection

Building Inspection · DFCU

Oct 21, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 30, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$40,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Seri Ngernwattana

Seri Ngerwattana, Pe

EngineerC66949
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202212309561 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record