4281 25th St
San Francisco permit 202212309573 · Noe Valley
Renovation of (e) single family home & basement addition.minor exterior window/door work.new building systems to accomodate new renovation scope of work.
- Filed
- Dec 30, 2022
- Issued
- Feb 13, 2025 (25 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 7 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 30, 2022 | Jan 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 10, 2023 | Dec 6, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 10, 2023 | Jan 28, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 11, 2023 | Apr 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Oct 10, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 15, 2024 | Feb 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 22, 2024 | Feb 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 26, 2024 | May 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 26, 2024 | Apr 26, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2024 | Mar 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2024 | Mar 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 4, 2024 | Oct 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 4, 2024 | Oct 10, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 4, 2024 | Oct 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 4, 2024 | Oct 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2024 | Oct 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2024 | Oct 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 5, 2024 | Jan 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2024 | Jan 10, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2024 | Jan 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 26, 2024 | Jan 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 26, 2024 | Dec 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2024 | Dec 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 16, 2025 | Jan 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Feb 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Pho Pho Architects | Architect | C-33844 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019