300 Grant Av
San Francisco permit 202301099843 · Financial District/South Beach
Install new stair case from basement floor to 2nd floor. new (2) bathrooms on the 1st floor.
- Filed
- Jan 9, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 27 stops across 5 departments
- Comments issued
- 8 times, by Planning, Fire Department, Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Plumbing inspector Building Inspection · PID-INSP | Jan 9, 2023 | Jan 9, 2023 | — |
Intake Building Inspection · INTAKE | Jan 9, 2023 | Jan 9, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 9, 2023 | Feb 2, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2023 | Jan 9, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2023 | Feb 2, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2023 | Jul 28, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 28, 2023 | Jul 28, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 15, 2023 | Aug 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 21, 2023 | Aug 21, 2023 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 22, 2023 | Aug 22, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Aug 25, 2023 | Aug 25, 2023 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2023 | Sep 15, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 15, 2023 | Oct 19, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 19, 2023 | Dec 14, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 19, 2023 | Dec 7, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Dec 12, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 18, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Dec 20, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 12, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 12, 2024 | Jan 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 18, 2024 | Feb 9, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 29, 2024 | Mar 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 13, 2024 | Mar 14, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 18, 2024 | Mar 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Mar 19, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2024 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $1,300,000
| Name | Role | License on permit |
|---|---|---|
| Jiwon Jung | Engineer | C-89281 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026