630 Alvarado St #0
San Francisco permit 202301109975 · Noe Valley
Permit to legalize original unit count (27). unit 305 & 306 demised to origianl unit confifuration and count (27). these units were combined without permit & have since been restored to their original configuration per approved use under pa#311252/15.
- Filed
- Jan 10, 2023
- Issued
- Feb 28, 2023 (2 months after filing)
- Completed
- Apr 19, 2023 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jan 10, 2023 | Jan 10, 2023 | — |
Intake Building Inspection · INTAKE | Jan 10, 2023 | Jan 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 31, 2023 | Jan 31, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 31, 2023 | Jan 31, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2023 | Feb 1, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 1, 2023 | Feb 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2023 | Feb 1, 2023 | — |
Development fee collection Building Inspection · DFCU | Feb 1, 2023 | Feb 1, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2023 | Feb 28, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Nathan C Simpson Nathan Simpson Architect | Architect | C37662 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025