1447 Thomas Av
San Francisco permit 202301130184 · Bayview Hunters Point
1st fl. reconfig.(e) living and garage, add a full bath, a kitchen, bedroom, office, and (1) sliding glass door at the rear of building not visable from a street or other public right-of-way), convert 1st floor into an adu per state program & legalization of all unpermitted work as shown on plans.
- Filed
- Jan 13, 2023
- Issued
- Apr 3, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- None
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 13, 2023 | Mar 22, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 22, 2023 | Dec 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 22, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 22, 2023 | Jul 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2023 | Jul 5, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2023 | Apr 4, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 22, 2023 | Mar 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 22, 2023 | Dec 29, 2023 | In Progress |
Building plan review Building Inspection · BLDG | Jul 17, 2023 | Aug 29, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2023 | Sep 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2023 | Jul 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2023 | Aug 23, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2023 | Aug 16, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 11, 2023 | Sep 12, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 2, 2023 | Dec 2, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 5, 2023 | Dec 28, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Dec 5, 2023 | Dec 5, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 29, 2023 | Apr 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $257,909
| Name | Role | License on permit |
|---|---|---|
| Young Woo Son Young Woo | Architect | C37446 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026