1871 15th Av
San Francisco permit 202301270923 · Inner Sunset
To erect a 1-story, 1-adu structure at the rear. type v-b.
- Filed
- Jan 27, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 27, 2023 | Feb 10, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 10, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | Feb 10, 2023 | Mar 7, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2023 | Mar 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 10, 2023 | Mar 22, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 10, 2023 | Mar 4, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2023 | Feb 13, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2023 | Feb 15, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 10, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Jesse Eugene Landers Design Everest | Engineer | C83060 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2014