638 Rhode Island St
San Francisco permit 202302031391 · Potrero Hill
Legalization of 3rd unit under ord 43-14 to include: 1 bedroom, 1 baths, living room, dining room, kitchen & laundry.(n) structural, electrical, plumbing as req.replacement of (e) west egres stairs. ref legalization pa on sheet a0.01.
- Filed
- Feb 3, 2023
- Issued
- Jun 11, 2024 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 36 stops across 6 departments
- Comments issued
- 15 times, by Building Inspection, Fire Department
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Feb 3, 2023 | Feb 3, 2023 | — |
Apartment and hotel inspection Building Inspection · HIS | Feb 3, 2023 | Feb 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 3, 2023 | Oct 11, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Feb 6, 2023 | Mar 22, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 22, 2023 | Sep 22, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2023 | Oct 6, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 26, 2023 | Nov 9, 2023 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 12, 2023 | Oct 12, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 13, 2023 | Oct 18, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Oct 25, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 1, 2023 | Nov 15, 2023 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Nov 7, 2023 | Nov 16, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2023 | Jan 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Nov 30, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 15, 2023 | Jan 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 18, 2023 | Dec 26, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 18, 2023 | Dec 19, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2024 | Jan 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 11, 2024 | Jan 17, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 11, 2024 | Jan 24, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 17, 2024 | Jan 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 19, 2024 | Jan 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Feb 14, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 6, 2024 | Feb 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Feb 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 15, 2024 | Mar 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 28, 2024 | Mar 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 29, 2024 | Apr 3, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 3, 2024 | Apr 10, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2024 | Apr 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2024 | Apr 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 17, 2024 | Apr 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 30, 2024 | May 15, 2024 | Approved |
Development fee collection Building Inspection · DFCU | May 21, 2024 | May 21, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | May 22, 2024 | Jun 6, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 6, 2024 | Jun 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $280,244
| Name | Role | License on permit |
|---|---|---|
| Andrew Johnston Rodgers Rodgers Architecture | Architect | C30697 |
| Kevin Eugene Brown Kevin Brown | Engineer | C-41834 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025