2717 Union St #2717
San Francisco permit 202302061458 · Marina
Add a private roof deck and stack new exterior access stairs to the roof above the (e) stair hall add a skylight above stair hall, replace (e) skylights
- Filed
- Feb 6, 2023
- Issued
- Jan 16, 2025 (23 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 6, 2023 | Feb 6, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 16, 2023 | Dec 12, 2023 | Approved |
Planning discretionary review Planning · CP-DR | Apr 13, 2023 | Oct 26, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 4, 2023 | Dec 13, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 15, 2023 | Dec 15, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 15, 2023 | Dec 15, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2023 | Dec 19, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Feb 14, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 19, 2023 | Dec 19, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 14, 2024 | Mar 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 1, 2024 | Mar 11, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 14, 2024 | Mar 14, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 18, 2024 | Mar 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Mar 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 21, 2024 | Apr 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 12, 2024 | Apr 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2024 | May 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 19, 2024 | Apr 19, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Apr 19, 2024 | Apr 19, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 29, 2024 | May 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2025 | Jan 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 8, 2025 | Jan 9, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 10, 2025 | Jan 10, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2025 | Jan 16, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $90,000
| Name | Role | License on permit |
|---|---|---|
| Martin C Kellogg Kellogg Architects | Architect | C-35171 |
| Kathryn Briggs Base Design | Engineer | S-5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025