196 Liberty St
San Francisco permit 202302162120 · Mission
Demolish int walls, new int wall layouts, increase size of garage door, new landscaping and repair (e) retaining walls in back yard, replace (e) stair in backyard. new ground floor second unit
- Filed
- Feb 16, 2023
- Issued
- Apr 12, 2024 (14 months after filing)
- Completed
- Jun 3, 2026 (26 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 48 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Public Utilities, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 16, 2023 | Mar 2, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Mar 2, 2023 | Dec 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 2, 2023 | Feb 29, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Oct 26, 2023 | Oct 31, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 13, 2023 | Jan 23, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2023 | Jan 3, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2023 | Dec 19, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2024 | Jan 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 26, 2024 | Jan 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 9, 2024 | Feb 13, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2024 | Feb 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 9, 2024 | Feb 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2024 | Feb 27, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Feb 29, 2024 | Apr 12, 2024 | Administrative |
Addendum 1: Grading, foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building pre-screening Building Inspection · PRE-BLDG | Apr 15, 2024 | Apr 15, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 15, 2024 | Apr 15, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Apr 15, 2024 | Apr 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2024 | Apr 22, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 19, 2024 | Apr 19, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | May 22, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2024 | Apr 30, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 22, 2024 | Dec 3, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 20, 2024 | May 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2024 | Jun 20, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2024 | Jun 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 2, 2024 | Jul 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2024 | Jul 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2024 | Dec 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 8, 2024 | Jul 8, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Oct 15, 2024 | Oct 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 25, 2024 | Dec 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 25, 2024 | Dec 3, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2024 | Oct 28, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 17, 2024 | Dec 17, 2024 | Approved |
Addendum 2: Superstructure, architectural, & title 24 energy
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2024 | Dec 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 16, 2024 | Dec 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 31, 2024 | Feb 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Jan 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 31, 2024 | Jan 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2024 | Jan 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2024 | Jan 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 31, 2024 | Feb 27, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2025 | Feb 4, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 6, 2025 | Feb 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2025 | Feb 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2025 | Feb 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2025 | Feb 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2025 | Mar 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Kurt R Melander Melander Architects | Architect | C27044 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025