550 Terry A Francois Bl
San Francisco permit 202302172178 · Mission Bay
The south portion of prj is core-shell,"warm shell only" renovation & being submitted for permit as a b-group occupancy. (e) building, both north & south portions, are b-group. (e) service elevator, elevator 5,will be upgraded to serve as a hazardous materials lift. life safety under separate permi
- Filed
- Feb 17, 2023
- Issued
- Aug 18, 2023 (6 months after filing)
- Completed
- Jan 16, 2025 (17 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- None
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 17, 2023 | Feb 27, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 27, 2023 | Jun 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2023 | Jun 1, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 27, 2023 | Jun 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2023 | Apr 10, 2023 | — |
Redevelopment review Redevelopment · REDEV | Feb 27, 2023 | Aug 3, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 27, 2023 | Aug 9, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Mar 22, 2023 | Jul 18, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2023 | Jul 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 24, 2023 | Jul 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 6, 2023 | Jul 17, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 17, 2023 | Jul 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2023 | Jul 17, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 8, 2023 | Aug 8, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2023 | Aug 18, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $30,000,000
| Name | Role | License on permit |
|---|---|---|
| Russell E Sherman | Architect | C26698 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026