1358 15th Av
San Francisco permit 202302172212 · Inner Sunset
First floor: rear yard deck addition second floor: add deck and stair. in-fill existing door. third floor: convert porch on third floor to enclosed conditioned space. roof: extend roof above new enclosed conditioned space below.
- Filed
- Feb 17, 2023
- Issued
- Nov 13, 2023 (9 months after filing)
- Completed
- Aug 16, 2024 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 23 stops across 2 departments
- Comments issued
- 5 times, by Building Inspection
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 17, 2023 | Feb 22, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2023 | Jul 17, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 22, 2023 | Oct 24, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | May 1, 2023 | Jul 17, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 17, 2023 | Aug 11, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2023 | Aug 21, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 23, 2023 | Aug 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 30, 2023 | Aug 30, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 5, 2023 | Oct 10, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Oct 6, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 20, 2023 | Sep 21, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 20, 2023 | Sep 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 12, 2023 | Oct 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 13, 2023 | Oct 10, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 13, 2023 | Oct 13, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2023 | Nov 13, 2023 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 1, 2023 | Dec 1, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Feb 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2023 | Jan 12, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 4, 2023 | Feb 15, 2024 | — |
Building plan review Building Inspection · BLDG | Feb 8, 2024 | Feb 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 8, 2024 | Feb 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2024 | Feb 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $84,309
| Name | Role | License on permit |
|---|---|---|
| Kelly Eleanor Manning Kelly Manning | Architect | C-34603 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025