1113 Hampshire St
San Francisco permit 202302212280 · Mission
Construct grd flr in-fill addition @ rear beneath (e) deck w/ steps & privacy screen firewall extend into reqd rear yard. convert (e) storage & laundry rm into primaty bedrm w/ full bath & laundry rm. construct interior stais to 2nd flr. remove rear bathrm & create bedrm. cp variance#2022000591var
- Filed
- Feb 21, 2023
- Issued
- Sep 29, 2023 (7 months after filing)
- Completed
- Aug 11, 2025 (22 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 21, 2023 | Feb 21, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 21, 2023 | Apr 26, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 21, 2023 | Sep 18, 2023 | In Progress |
Planning neighborhood notice Planning · CP-NP | Feb 23, 2023 | Apr 26, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2023 | Aug 23, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 26, 2023 | May 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2023 | Apr 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2023 | May 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 6, 2023 | Aug 25, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jul 6, 2023 | Aug 9, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 6, 2023 | Jul 6, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2023 | Aug 25, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2023 | Jul 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2023 | Aug 24, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Jul 28, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 23, 2023 | Aug 23, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2023 | Aug 25, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2023 | Sep 18, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 18, 2023 | Sep 29, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Vladimir Rabichev Optimal Design Group | Engineer | C35314 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2018