CheckMyDesigner

141 Retiro Wy

San Francisco permit 202302242568 · Marina

OtherFull plan reviewComplete
Street view · Apr 2019
Google Street View of 141 Retiro Wy, Apr 2019
Scope of work
As written on the permit application.

Replace windows and door at front of bldg.add garage door and pedestrian door to carport.replace wood siding with stucco.

Timeline
Key dates from the city record.
Filed
Feb 24, 2023
Issued
Jan 22, 2024 (11 months after filing)
Completed
Jun 10, 2025 (17 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
4 times, by Building Inspection, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 1, 2023—

Zoning review

Planning · CP-ZOC

Jul 20, 2023—

Permit Processing Center

Building Inspection · PPC

Jan 11, 2024—

Building plan review

Building Inspection · BLDG

Aug 23, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 4, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 16, 2023Approved

Building plan review

Building Inspection · BLDG

Oct 2, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 27, 2023Approved

Zoning review

Planning · CP-ZOC

Oct 2, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 2, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 1, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 21, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 6, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Dec 4, 2023Approved

Fire prevention review

Fire Department · SFFD

Dec 14, 2023Approved

Zoning review

Planning · CP-ZOC

Jan 8, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 19, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jan 5, 2024Approved

Fire prevention review

Fire Department · SFFD

Jan 10, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 22, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Jan 22, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$100,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Lincoln Lighthill

Lincoln Lighthill Architecture

ArchitectC34466
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202302242568 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record