141 Retiro Wy
San Francisco permit 202302242568 · Marina
Replace windows and door at front of bldg.add garage door and pedestrian door to carport.replace wood siding with stucco.
- Filed
- Feb 24, 2023
- Issued
- Jan 22, 2024 (11 months after filing)
- Completed
- Jun 10, 2025 (17 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 24, 2023 | Mar 1, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 1, 2023 | Jul 20, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 1, 2023 | Jan 11, 2024 | — |
Building plan review Building Inspection · BLDG | Jul 24, 2023 | Aug 23, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2023 | Aug 23, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 24, 2023 | Dec 4, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2023 | Aug 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2023 | Oct 2, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2023 | Sep 27, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 22, 2023 | Oct 2, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2023 | Oct 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 27, 2023 | Nov 1, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 3, 2023 | Nov 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2023 | Nov 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2023 | Dec 4, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 14, 2023 | Dec 14, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2023 | Jan 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 18, 2023 | Dec 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2023 | Jan 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 18, 2023 | Jan 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2023 | Dec 22, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 11, 2024 | Jan 22, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Lincoln Lighthill Lincoln Lighthill Architecture | Architect | C34466 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019