1899 Oakdale Av
San Francisco permit 202302272706 · Bayview Hunters Point
Comply w/ nov #202292335. 1820 sq ft of fire dmg repair & 200 sq ft remodel. remodel: new bedrm & closet at 2/fl unit. repair as follows: remove & replace damaged roofing, roof sheathing, framing, windows, doors, siding, drywall, insulation, test electrical, remove & replace damaged elec.
- Filed
- Feb 27, 2023
- Issued
- Jan 8, 2025 (22 months after filing)
- Completed
- Aug 27, 2026 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 47 stops across 4 departments
- Comments issued
- 10 times, by Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 27, 2023 | Mar 6, 2023 | — |
Code enforcement Building Inspection · CES | Mar 3, 2023 | Mar 3, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 6, 2023 | Oct 18, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 6, 2023 | Dec 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 18, 2023 | Dec 4, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2023 | Dec 8, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 18, 2023 | Dec 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2023 | Nov 2, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2023 | Nov 3, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2023 | Dec 11, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jan 10, 2024 | Jan 11, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 10, 2024 | Jan 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 10, 2024 | Jan 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 10, 2024 | Jan 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 10, 2024 | Jan 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 1, 2024 | Feb 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Feb 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Feb 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2024 | Feb 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 14, 2024 | Feb 14, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 19, 2024 | Apr 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 19, 2024 | Apr 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 19, 2024 | May 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 19, 2024 | Apr 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 19, 2024 | Apr 25, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 24, 2024 | Jul 24, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 13, 2024 | Sep 17, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 13, 2024 | Sep 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 13, 2024 | Sep 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2024 | Sep 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2024 | Sep 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 26, 2024 | Oct 4, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 26, 2024 | Sep 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2024 | Oct 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2024 | Oct 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2024 | Sep 30, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 18, 2024 | Oct 31, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 18, 2024 | Oct 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 18, 2024 | Oct 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2024 | Oct 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2024 | Oct 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 5, 2024 | Nov 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 5, 2024 | Nov 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 5, 2024 | Nov 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2024 | Nov 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2024 | Dec 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2024 | Jan 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Mark Paul Rivera Powell And Associates | Architect | C66864 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023