424 A Texas St
San Francisco permit 202302282730 · Potrero Hill
1 new adu per ordinance #95-17 associated with new construction of single family home filed under bpa#202205134264
- Filed
- Feb 28, 2023
- Issued
- Nov 6, 2024 (20 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 35 stops across 5 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 28, 2023 | Feb 28, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 28, 2023 | May 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 28, 2023 | May 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2023 | Sep 7, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 28, 2023 | May 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2023 | Mar 2, 2023 | — |
Urban forestry Public Works · DPW-BUF | Feb 28, 2023 | Mar 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2023 | Mar 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 28, 2023 | Oct 9, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2023 | Aug 30, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 29, 2023 | Aug 30, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2023 | Aug 31, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 28, 2023 | Oct 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2023 | Oct 30, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 28, 2023 | Sep 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2023 | Oct 12, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 2, 2023 | Nov 20, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 20, 2024 | Aug 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 20, 2024 | Aug 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2024 | Aug 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2024 | Aug 21, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 20, 2024 | Aug 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2024 | Aug 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2024 | Aug 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2024 | Sep 12, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 12, 2024 | Sep 12, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Sep 12, 2024 | Sep 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 18, 2024 | Oct 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2024 | Oct 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 18, 2024 | Sep 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2024 | Sep 19, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 18, 2024 | Oct 2, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2024 | Sep 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 3, 2024 | Oct 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 9, 2024 | Nov 6, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $165,000
| Name | Role | License on permit |
|---|---|---|
| Beverly Ann Choe Bach Architecture | Architect | C29098 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022