424 A Texas St

San Francisco permit 202302282730 · Potrero Hill

ADUFull plan reviewIssued
Street view · Apr 2022
Google Street View of 424 A Texas St, Apr 2022
Scope of work
As written on the permit application.

1 new adu per ordinance #95-17 associated with new construction of single family home filed under bpa#202205134264

Timeline
Key dates from the city record.
Filed
Feb 28, 2023
Issued
Nov 6, 2024 (20 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
35 stops across 5 departments
Comments issued
Twice, by Building Inspection, Fire Department
Put on hold
5 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 28, 2023—

Zoning review

Planning · CP-ZOC

May 30, 2024Approved

Building plan review

Building Inspection · BLDG

May 7, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 7, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

May 24, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 2, 2023—

Urban forestry

Public Works · DPW-BUF

Mar 15, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 22, 2023—

Permit Processing Center

Building Inspection · PPC

Oct 9, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Aug 30, 2023Approved

Urban forestry

Public Works · DPW-BUF

Aug 30, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 31, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 6, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 30, 2023Approved

Urban forestry

Public Works · DPW-BUF

Sep 29, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 12, 2023Approved

Urban forestry

Public Works · DPW-BUF

Nov 20, 2023Approved

Fire prevention review

Fire Department · SFFD

Aug 23, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 30, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 21, 2024Approved

Urban forestry

Public Works · DPW-BUF

Aug 20, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 23, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 21, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 12, 2024Approved

Building plan review quality control

Building Inspection · BLDG-QC

Sep 12, 2024Administrative

Development fee collection

Building Inspection · DFCU

Sep 12, 2024Administrative

Zoning review

Planning · CP-ZOC

Oct 2, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 9, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 24, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Sep 19, 2024Approved

Urban forestry

Public Works · DPW-BUF

Oct 2, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Sep 20, 2024Approved

Fire prevention review

Fire Department · SFFD

Oct 3, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$165,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Beverly Ann Choe

Bach Architecture

ArchitectC29098
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202302282730 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record