1760 Union St #0
San Francisco permit 202303063078 · Marina
Convert 660 sf of (e) garage to (n) adu under the state program. (n) deck at rear w/ stairs to rear yard and crawl space below. 1 (n) window & 1 (n) sliding glass door at level 1, adu.
- Filed
- Mar 6, 2023
- Issued
- Aug 28, 2023 (6 months after filing)
- Completed
- May 27, 2025 (21 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- None
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 6, 2023 | Mar 17, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 17, 2023 | Jul 14, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 17, 2023 | Jul 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2023 | Jul 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 17, 2023 | Mar 23, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 17, 2023 | Mar 20, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 17, 2023 | Jul 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2023 | Mar 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 17, 2023 | Aug 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 14, 2023 | Jul 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2023 | Jul 20, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 25, 2023 | Aug 1, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2023 | Jul 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2023 | Aug 1, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 9, 2023 | Aug 9, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 9, 2023 | Aug 10, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 9, 2023 | Aug 14, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 9, 2023 | Aug 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2023 | Aug 10, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 17, 2023 | Aug 17, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 17, 2023 | Aug 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $179,603
| Name | Role | License on permit |
|---|---|---|
| Jason Park Langkammerer At6 Architecture Design | Architect | C28796 |
| Nate Williams Mosswood Engineering | Engineer | C62068 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025