2319 Funston Av
San Francisco permit 202303083267 · West of Twin Peaks
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa# 202112174643, change deck structure from steel to wood, extend master bedroom 75sqft beyond previous permit.
- Filed
- Mar 8, 2023
- Issued
- Sep 18, 2024 (18 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 8, 2023 | Mar 8, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Mar 8, 2023 | Mar 8, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 26, 2023 | Apr 26, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2023 | Feb 29, 2024 | Approved |
Planning neighborhood notice Planning · CP-NP | Feb 7, 2024 | Feb 9, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 29, 2024 | Apr 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 30, 2024 | Apr 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2024 | Jun 11, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2024 | Jul 1, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 1, 2024 | Jul 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2024 | Jul 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2024 | Jul 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2024 | Jul 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 1, 2024 | Sep 10, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2024 | Jul 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 20, 2024 | Aug 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2024 | Aug 26, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 20, 2024 | Sep 10, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2024 | Aug 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2024 | Sep 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 5, 2024 | Sep 10, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2024 | Sep 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 10, 2024 | Sep 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2024 | Sep 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Ines Lejarraga Lejarraga Studio | Architect | C32744 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025