525 Market St
San Francisco permit 202303143634 · Financial District/South Beach
Suite 120 on 1/f: t.i, demo of non structural partitions and storefront, and building new non-structural partitions and storefront at building facade. (scope includes 294sf of g/f area back to original wall dimensions per 1973 construction)
- Filed
- Mar 14, 2023
- Issued
- Sep 11, 2023 (6 months after filing)
- Completed
- Jul 2, 2025 (22 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 14, 2023 | Mar 14, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 14, 2023 | Mar 14, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 16, 2023 | Mar 16, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 16, 2023 | Mar 16, 2023 | — |
Intake Building Inspection · INTAKE | Mar 28, 2023 | Mar 28, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 28, 2023 | Mar 28, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 28, 2023 | Mar 28, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 6, 2023 | Apr 6, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 6, 2023 | Apr 6, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 6, 2023 | Apr 6, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 6, 2023 | Apr 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 6, 2023 | Apr 6, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 6, 2023 | Apr 6, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Apr 6, 2023 | Apr 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 6, 2023 | Apr 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 21, 2023 | Apr 21, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Apr 28, 2023 | Apr 28, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 28, 2023 | Apr 28, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2023 | Apr 28, 2023 | — |
Building plan review Building Inspection · BLDG | May 18, 2023 | May 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2023 | Jun 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2023 | Jun 28, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2023 | Sep 11, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2023 | Sep 11, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $692,110
| Name | Role | License on permit |
|---|---|---|
| Ariane Lebrilla Asd/Sky | Architect | C38312 |
| David Loren Byrne | Engineer | C84773 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026