72 Harper St
San Francisco permit 202303163798 · Glen Park
3 story rear addition,convert 1st fl to adu,elevate portion of roof,interior partition changes on all fls,construct excavated rear yard light court,re-build front steps in kind to met egress code,install fire sprinkler stystem,full seismic upgrade of bldg,new fixtures fitting & finishes throughout.
- Filed
- Mar 16, 2023
- Issued
- Jun 24, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 77 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Permit Center, Planning
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 16, 2023 | Mar 24, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 24, 2023 | Feb 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 24, 2023 | May 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2023 | Apr 4, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 24, 2023 | Apr 25, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2023 | Mar 29, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 24, 2023 | Jun 6, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 4, 2023 | Aug 11, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jun 16, 2023 | Jun 20, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2023 | Jun 21, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 16, 2023 | Jul 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2023 | Jun 22, 2023 | — |
Urban forestry Public Works · DPW-BUF | Aug 17, 2023 | Sep 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 17, 2023 | Aug 24, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2023 | Aug 23, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2023 | Aug 23, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 17, 2023 | Jun 5, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Sep 14, 2023 | Sep 22, 2023 | Administrative |
Planning discretionary review Planning · CP-DR | Nov 8, 2023 | Nov 14, 2023 | Administrative |
Planning discretionary review Planning · CP-DR | Nov 11, 2023 | Nov 17, 2023 | Administrative |
Planning discretionary review Planning · CP-DR | Nov 11, 2023 | May 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Mar 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Mar 14, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 22, 2024 | Feb 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2024 | Feb 27, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 22, 2024 | Mar 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2024 | Feb 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 7, 2024 | Mar 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 8, 2024 | May 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 8, 2024 | Mar 20, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 8, 2024 | Mar 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2024 | Mar 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 23, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 13, 2024 | May 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 16, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 13, 2024 | May 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 6, 2024 | Jun 24, 2024 | Administrative |
Addendum 1: Excavation, foundation & superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 17, 2024 | Jul 29, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 24, 2024 | Jul 24, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 24, 2024 | Jul 24, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Jul 25, 2024 | Jul 25, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 5, 2024 | Aug 15, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 14, 2024 | Aug 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2024 | Aug 28, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 28, 2024 | Sep 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2024 | Aug 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 28, 2024 | Jan 15, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 23, 2024 | Sep 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 17, 2024 | Oct 22, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 29, 2024 | Nov 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2024 | Nov 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2024 | Oct 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2024 | Dec 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 3, 2025 | Jan 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 3, 2025 | Jan 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 3, 2025 | Jan 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 10, 2025 | Jan 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2025 | Feb 21, 2025 | Administrative |
Addendum 2: Arch, mech, t-24, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 21, 2025 | Apr 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2025 | Apr 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2025 | Apr 23, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 8, 2025 | May 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 8, 2025 | Apr 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 8, 2025 | Apr 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2025 | Apr 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2025 | Apr 15, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 8, 2025 | Jul 22, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | May 14, 2025 | May 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2025 | Jul 7, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 2, 2025 | Jul 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 2, 2025 | Jul 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 2, 2025 | Jul 11, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2025 | Jul 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2025 | Jul 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 7, 2025 | Jul 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 22, 2025 | Sep 5, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $985,000
| Name | Role | License on permit |
|---|---|---|
| Dennis C Budd Dennis Budd Aia Architect | Architect | C26969 |
| Erevan O'neill One Design | Engineer | C75459 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025