1 Mallorca Wy

San Francisco permit 202303173911 · Marina

ADUFull plan reviewComplete
Street view · Jan 2025
Google Street View of 1 Mallorca Wy, Jan 2025
Scope of work
As written on the permit application.

Construction of 3 adu units on 1/f. no excavation.no change to egress or occ.removal of non-structural walls, add new walls, cabinets,apppliances,plumb fixtures/finishes.new electrical receptacles, communication outlets, lighting & ventilation. install heat pumps. sidewalk work. 3 street trees.

Timeline
Key dates from the city record.
Filed
Mar 17, 2023
Issued
Jul 19, 2024 (16 months after filing)
Completed
Jan 29, 2025 (6 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 5 departments
Comments issued
11 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 5, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Sep 15, 2023Administrative

Zoning review

Planning · CP-ZOC

Oct 10, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 27, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 17, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 28, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 20, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 2, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 18, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jan 2, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 2, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 21, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 27, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 5, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 12, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 21, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 29, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 8, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 15, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 23, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 2, 2024Administrative

Fire prevention review

Fire Department · SFFD

Jul 17, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 10, 2024Approved

Development fee collection

Building Inspection · DFCU

Jul 17, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jul 19, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$900,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Terryl Marshall Lofrano

Lofrano Arch/Sculpture Design

ArchitectC-7292
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202303173911 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record