1 Mallorca Wy
San Francisco permit 202303173911 · Marina
Construction of 3 adu units on 1/f. no excavation.no change to egress or occ.removal of non-structural walls, add new walls, cabinets,apppliances,plumb fixtures/finishes.new electrical receptacles, communication outlets, lighting & ventilation. install heat pumps. sidewalk work. 3 street trees.
- Filed
- Mar 17, 2023
- Issued
- Jul 19, 2024 (16 months after filing)
- Completed
- Jan 29, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 27 stops across 5 departments
- Comments issued
- 11 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 17, 2023 | Sep 5, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2023 | Sep 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 15, 2023 | Oct 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 15, 2023 | Sep 27, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2023 | Oct 17, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Sep 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2023 | Sep 20, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Oct 2, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 15, 2023 | Jul 18, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 2, 2024 | Jan 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 2, 2024 | Jan 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2024 | Feb 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2024 | Feb 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 5, 2024 | Mar 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 12, 2024 | Mar 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2024 | Mar 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2024 | Mar 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2024 | Mar 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2024 | Apr 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2024 | Apr 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 23, 2024 | Apr 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2024 | Jul 2, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jul 3, 2024 | Jul 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 3, 2024 | Jul 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 3, 2024 | Jul 10, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jul 17, 2024 | Jul 17, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 18, 2024 | Jul 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $900,000
| Name | Role | License on permit |
|---|---|---|
| Terryl Marshall Lofrano Lofrano Arch/Sculpture Design | Architect | C-7292 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025