2550 Ulloa St
San Francisco permit 202303214119 · Sunset/Parkside
1st fl: new adu. convert 168 sqft of garage to adu, remodel (e) bathrm & add kitchen, 2 new egress windows at bedrm, widen (e) entry door. 2nd fl: remodel (e) kitchen & bathrm in kind, add 1 full bathrm, remove (e) door to rear deck, patch stucco to match adjacent wall, remove (e) rear deck.
- Filed
- Mar 21, 2023
- Issued
- Oct 11, 2023 (7 months after filing)
- Completed
- Sep 13, 2024 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 23 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 21, 2023 | Mar 31, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 31, 2023 | Sep 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 31, 2023 | May 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2023 | Sep 5, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2023 | Apr 4, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2023 | Sep 14, 2023 | In Progress |
Building plan review Building Inspection · BLDG | May 25, 2023 | May 26, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 21, 2023 | Aug 21, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 13, 2023 | Sep 13, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2023 | Sep 14, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2023 | Oct 11, 2023 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 6, 2023 | Nov 6, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 6, 2023 | Jan 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Jan 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 6, 2023 | Nov 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2023 | Nov 8, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 6, 2023 | Feb 8, 2024 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 17, 2024 | Jan 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2024 | Jan 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2024 | Feb 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2024 | Feb 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2024 | Feb 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 8, 2024 | Feb 13, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $280,903
| Name | Role | License on permit |
|---|---|---|
| Ian Robert Glidden Ian Glidden, Architect | Authorized agent-others | C29209 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020