551 Alvarado St
San Francisco permit 202303224205 · Noe Valley
(n) vertical & horizontal addition @ grd flr, legalize unauthorized dwelling unit & convert portion to (n) garage. reconfigure rooms @ 2nd flr. raise portion of roof & convert (e) attic to 3rd flr. convert portion of (e) crawlspace to (n) basement.
- Filed
- Mar 22, 2023
- Issued
- Feb 9, 2024 (11 months after filing)
- Completed
- Oct 22, 2026 (32 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 44 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 22, 2023 | Mar 28, 2023 | — |
Code enforcement Building Inspection · CES | Mar 27, 2023 | Mar 27, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 28, 2023 | Sep 28, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 28, 2023 | Jan 30, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Aug 11, 2023 | Aug 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 28, 2023 | Oct 23, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 28, 2023 | Nov 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2023 | Sep 30, 2023 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 28, 2023 | Oct 26, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2023 | Oct 16, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 27, 2023 | Nov 27, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Nov 29, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 9, 2024 | Jan 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 9, 2024 | Jan 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2024 | Jan 29, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2024 | Jan 10, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jan 29, 2024 | Jan 30, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2024 | Feb 9, 2024 | Administrative |
Addendum 1: Grading, foundation, steel frame, superstructure, t-24, final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 13, 2024 | Feb 21, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 14, 2024 | Feb 14, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2024 | Feb 22, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Feb 15, 2024 | Feb 15, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 15, 2024 | Feb 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Mar 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 22, 2024 | Mar 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Apr 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 22, 2024 | Apr 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2024 | Feb 27, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2024 | Feb 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 22, 2024 | Jul 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 20, 2024 | Apr 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2024 | Apr 1, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 2, 2024 | Apr 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 12, 2024 | Apr 12, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2024 | Jun 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2024 | Jun 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 6, 2024 | Jun 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 21, 2024 | Jun 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2024 | Jun 25, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 26, 2024 | Jun 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 27, 2024 | Jul 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2024 | Jun 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2024 | Jun 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2024 | Jul 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $925,000
| Name | Role | License on permit |
|---|---|---|
| P Vincent Gonzaga Vincent Gonzaga Architect | Architect | C33614 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025