150 Stockton St #0
San Francisco permit 202303234285 · Financial District/South Beach
Store in store interior only build with new non-load bearng walls, finishes, elec fixtures, and wiring, hvac work
- Filed
- Mar 23, 2023
- Issued
- Aug 28, 2023 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 16 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 23, 2023 | Mar 23, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 23, 2023 | Mar 23, 2023 | — |
Intake Building Inspection · INTAKE | May 3, 2023 | May 3, 2023 | — |
Zoning review Planning · CP-ZOC | May 3, 2023 | May 3, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2023 | May 3, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 3, 2023 | May 3, 2023 | — |
Building plan review Building Inspection · BLDG | May 9, 2023 | May 9, 2023 | — |
Fire prevention review Fire Department · SFFD | May 9, 2023 | May 9, 2023 | — |
Intake Building Inspection · INTAKE | Jun 23, 2023 | Jun 23, 2023 | — |
Intake Building Inspection · INTAKE | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Aug 3, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 3, 2023 | Aug 3, 2023 | Approved |
Intake Building Inspection · INTAKE | Aug 8, 2023 | Aug 8, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 8, 2023 | Aug 8, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 10, 2023 | Aug 10, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 28, 2023 | Aug 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $165,000
| Name | Role | License on permit |
|---|---|---|
| Louis Loria Atmosphere Design & Architect | Architect | C-31289 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026