25 Vesta St
San Francisco permit 202303294675 · Bayview Hunters Point
Legalize dwelling unit @ ground fl & legalize laundry area in rear 2nd fl in response to nov #202182267. interior remodel of ground and 2nd floor. bpa #881769 consisted of a 2-story horizontal addition. cfc #9604878 completed aforementioned permit.g/f & 2/f remodel. added unit will be 25a vesta st.
- Filed
- Mar 29, 2023
- Issued
- Jun 12, 2025 (26 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 40 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 30, 2023 | Apr 24, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Apr 24, 2023 | Mar 13, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 5, 2024 | Mar 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 14, 2024 | Apr 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 4, 2024 | Apr 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2024 | Apr 26, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 9, 2024 | May 22, 2024 | Approved-Stipulated |
Building plan review quality control Building Inspection · BLDG-QC | Apr 26, 2024 | Apr 26, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 23, 2024 | May 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 29, 2024 | Jun 14, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 29, 2024 | Jun 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2024 | Aug 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 16, 2024 | Sep 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 17, 2024 | Sep 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2024 | Sep 27, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 30, 2024 | Nov 14, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2024 | Nov 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 22, 2024 | Mar 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 12, 2025 | Mar 12, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2025 | Jun 12, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2025 | Jan 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2026 | Jan 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Feb 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2026 | Feb 27, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Feb 24, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 21, 2026 | Feb 25, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Jan 22, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 21, 2026 | Jun 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 26, 2026 | Jun 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 26, 2026 | Jun 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 26, 2026 | Jun 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 26, 2026 | Jun 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 26, 2026 | May 28, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 26, 2026 | Jun 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 26, 2026 | May 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2026 | Aug 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $265,869
| Name | Role | License on permit |
|---|---|---|
| Sandra L Chan Studio Paz | Architect | 27326 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2017