Scope of work
As written on the permit application.

Extend (e) 1st room to rear lot. the addition is a family room with full bath and kitchenette. extend (e) 2nd flr deck over the top of the addition. the stair from the deck is relocated to the side.

Timeline
Key dates from the city record.
Filed
Mar 30, 2023
Issued
Mar 18, 2024 (12 months after filing)
Completed
Oct 16, 2025 (19 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
Once, by Building Inspection
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 4, 2023—

Zoning review

Planning · CP-ZOC

Sep 21, 2023Approved

Permit Processing Center

Building Inspection · PPC

Nov 30, 2023Administrative

Planning neighborhood notice

Planning · CP-NP

Aug 10, 2023Administrative

Building plan review

Building Inspection · BLDG

Oct 13, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 3, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 19, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 29, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 21, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 24, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Mar 18, 2024Administrative

Addendum 1: Final plans

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 25, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Mar 20, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Mar 22, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 22, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Mar 26, 2024Administrative

Building plan review

Building Inspection · BLDG

May 15, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 10, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 28, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jun 14, 2024Administrative

Building plan review

Building Inspection · BLDG

Jun 3, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 13, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 14, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 5, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jun 14, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$174,979
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Judith Ann Mattingly

Mattingly Thaler Archit.

ArchitectC23854
Robert Hugh Shaffer

Morris Shaffer Engineering

EngineerC45322
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202303304778 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record