858 25th Av
San Francisco permit 202303304778 · Outer Richmond
Extend (e) 1st room to rear lot. the addition is a family room with full bath and kitchenette. extend (e) 2nd flr deck over the top of the addition. the stair from the deck is relocated to the side.
- Filed
- Mar 30, 2023
- Issued
- Mar 18, 2024 (12 months after filing)
- Completed
- Oct 16, 2025 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 30, 2023 | Apr 4, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 4, 2023 | Sep 21, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 4, 2023 | Nov 30, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jul 24, 2023 | Aug 10, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 22, 2023 | Oct 13, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2023 | Oct 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2023 | Oct 19, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 20, 2023 | Nov 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 20, 2023 | Nov 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 20, 2023 | Oct 24, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 30, 2023 | Mar 18, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 18, 2024 | Mar 25, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 20, 2024 | Mar 20, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 22, 2024 | Mar 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 22, 2024 | Mar 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2024 | Mar 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | May 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 26, 2024 | Apr 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 26, 2024 | Apr 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 26, 2024 | Mar 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 26, 2024 | Jun 14, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 31, 2024 | Jun 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 31, 2024 | Jun 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 31, 2024 | Jun 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2024 | Jun 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 14, 2024 | Jun 14, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $174,979
| Name | Role | License on permit |
|---|---|---|
| Judith Ann Mattingly Mattingly Thaler Archit. | Architect | C23854 |
| Robert Hugh Shaffer Morris Shaffer Engineering | Engineer | C45322 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026