222 Webster St
San Francisco permit 202304055116 · Hayes Valley
Legalize an existing unwarranted gr floor unit ( soft story already completed and finaled)
- Filed
- Apr 5, 2023
- Issued
- Oct 25, 2024 (19 months after filing)
- Completed
- Jun 23, 2025 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 5, 2023 | Apr 5, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Apr 11, 2023 | Apr 11, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2023 | Apr 26, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2023 | Apr 27, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2023 | Sep 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2023 | Oct 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 11, 2023 | Oct 11, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2023 | Nov 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 15, 2023 | Nov 30, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 30, 2023 | Nov 30, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2023 | Dec 1, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2023 | Dec 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jun 11, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 11, 2024 | Jul 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 22, 2024 | Jul 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 30, 2024 | Aug 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2024 | Aug 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 12, 2024 | Sep 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2024 | Sep 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2024 | Sep 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2024 | Sep 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 30, 2024 | Oct 10, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Oct 11, 2024 | Oct 11, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Oct 11, 2024 | Oct 11, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 11, 2024 | Oct 25, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $119,375
| Name | Role | License on permit |
|---|---|---|
| Luis Antonio Robles Robles & Assocciates | Architect | C-21700 |
| Timothy Michael O'sullivan Tim O'sullivan Structural Eng | Engineer | C35235 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025